OTHER BUSINESS:
013-1: CITY HALL FACILITY
Council Discussion and Review of:
1. Current Proposal for City Hall Repairs
2. Alternative Options for City Hall Facility
3. Temporary City Hall Facilities and Locations
ADJOURNMENT
INTERIM CITY MANAGER
MIKE CALDWELL
CITY ATTORNEY
WAYNE TANAKA
CITY CLERK
RACHELBAKER
6:30 PM
Recommendation: Discuss and review items outlined above, provide direction to staff
and consider action on one or more of the following motions:
1. To authorize an increase in the project budget
2. To authorize the City Manager to enter into agreements/leases for temporary
City Hall
3. To postpone the project.
Next Regular Meeting: Monday, May 12, 2008; 6:30 pm
Medina City Hall d 501 Evergreen Point Road • Medina WA 98039
425-233-6400 ph + 425-454-8490 fx • www.medina-wii.gov
ITEM OB-1
CITY OF MEDINA
Public Works Department
January 31, 2008
TO: MAYOR AND CITY COUNCIL
FROM: DIRECTOR OF PUBLIC WORKS
SUBJECT: CITY HALL RENOVATION
RECOMMENDATION
It is recommended that the Mayor and Council Members authorize the "Call for
Bids" for the renovation of the Medina City Hall.
POLICY IMPLICATION
This action is consistent with the adopted City Capital Improvement Program for
2008-2013 and the adopted City Budget for 2008.
BACKROUND
The City consultant, Johnston Architects, have completed the contract
documents and plans for the renovation of the City Hall. The work detailed within the
contract documents includes those items identified in the City Hall Building Survey
Report of December 2006 that primarily address life and safety deficiencies. The work
briefly described includes: the replacement of the outside deck surface, siding
replacement on the south wall of City Hall, new exterior doors on the south and west
sides of the main floor of the building, two new interior support beams, interior shear
wall and seismic connections to the foundation and between the walls and the roof
rafters, replacement of the basement outside restroom fixtures and heaters, new
heating and ventilation system, electrical wiring upgrades, painting and carpeting of the
entire building following the repairs to the building envelope and interior walls.
The estimated project cost is $ 730,000 (see the attachment) which includes a
10% construction contingency. The project budget is $ 760,000. An alternate bid item
for new lighting fixtures will be included in the documents for consideration should
sufficient funds be available to improve the building lighting.
The proposed City Hall construction project schedule is as follows:
Council authorization to "Call for Bids" (February 11)
Advertise for Bids (February 12th and February 19th)
Open Bids (March 4th)
Award the Contract (March 10tn)
Construction (April to early September)
ITEM OB-1
DISCUSSION
An alternative City Hall location is being pursued at this time to reduce
interference with the work, reduce the contractors risk, limit the liability exposure, and to
provide adequate facilities rather than occupy the building during the work. Preliminary
discussions with the 1 st Church of Christian Science indicated that their site would
accommodate two stand alone portable trailers in their south parking lot at a rate of
$4,000 per month. Should this prove to be the most advantages, City Hall would be
temporarily relocated into the portables at an estimated total cost of approximately
$49,000 for five months. Other options such as renting or leasing a vacant house are
being pursued as well.
FISCAL CONSIDERATIONS AND IMPACT
Funds for the award of the bid are available in the Council -approved 2008 FY
budget. Funding for the alternate lighting and temporary City Hall may exceed the
present budget of $ 760,000 should that become necessary, the additional funds may
either be appropriated from the cash reserves or from other line items within the
adopted budget.
LEGAL REVIEW
This report has been submitted to the City Manager's Office for review.
Prepared by:
Joe Willis Sr, Director of Public Works
Attachment:
Project cost estimate
MEDINA CITY HALL RENOVATION
MEDINA CITY
CONSTRUCTION DOCUMENTS ESTIMATE SUMMARY
September 28, 2007
Existing & New Addition Bldg
Evidence Room Upgrade
ITEM OB-1
$597,425
$6,913
Total Project Cost $604,338
5�l �
7�AQ
n,, i-6
/2,, 0,?
G0!J -o
PROJECT: MEDINA CITY HALL RENOVATION - BASE
LOCATION: MEDINA, WA
BLDG SF: 4,325
ESTIMATE: 2007161
EST TYPE: CONSTRUCTION DOCUMENTS
DIVISION
DESCRIPTION
TOTAL
$/SF
A10
FOUNDATIONS
3,674
0.85
B10
SUPERSTRUCTURE
24,973
5.77
B20
EXTERIOR CLOSURE
55,352
12.80
B30
ROOFING
35,977
8.32
C10
INTERIOR CONSTRUCTION
10,080
2.33
C2O -
STAIRS
25,7Q0
5.94
C30
INTERIOR FINISHES
64,185
14.84
D20
PLUMBING
3,557
0.82
D30
HVAC
84,339
19.50
D50
ELECTRICAL
80,000
18.50
F20
SELECTIVE BUILDING DEMOLITION
19,321
4.47
G1O
SITE PREPARATION
202
0.05
G20
SITE IMPROVEMENTS
2,432
0,56
G30
SITE CIVIL / MECHANICAL UTILITIES
875
0.20
Z10
GENERAL REQUIREMENTS
105,000
24.28.
ESTIMATE SUBTOTAL
515,667
119.23
DESIGN CONTINGENCY @
5.00% 25,783
SUBTOTAL
541,450
ESCALATION TO 23-NOV-07 (8.00%NR) @
1.23% 6,646
SUBTOTAL
548,096
GENERAL CONTRACTOR'S OH & P @
9.00% 49,329
TOTAL
597,425
138.13
EXCLUSIONS:
SEE ESTIMATE SUMMARY
12/10/2007 9:39 AM MEDINA CITY HALL RENOVATION - BASE SUMMARY PAGE 1
PROJECT: MEDINA CITY HALL RENOVATION - BASE
ITEM OB-1
LOCATION: MEDINA, WA
BLDG SF: 4,325
ESTIMATE: 2007161
EST TYPE: CONSTRUCTION DOCUMENTS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL $lSF
A10
FOUNDATIONS
02000
DEMOISAWCUT SLAB
128 SF
6.00
768
02200
FOUNDATION BACKFILL - HAND
6 CY
25.00
150
02315
EXCAVATE FOUNDATIONS - HAND
8 CY
25.00
200
02315
HAUL/DUMP EXCESS EXCAVATION
1 LS
100
100
03000
4" SLAB ON GRADE @ STORAGE
128 SF
6.50
832
03000
CONC FOOTING
2 CY
500
1,000
03310
CONC-PERIMETER STEM WALL
16 SF
35.00
560
07260
VAPOR BARRIER STORAGE
128 SF
0.50
64 -
A10
FOUNDATIONS
DIVISION TOTAL
3,674 0.85
B10 SUPERSTRUCTURE
05100
EPDXY BOLTINGIANCHORING
13 EA
65.00
845
06090
MISC FRAMINGISEISMIC HARDWARE- EXISTING ROOF
2,832 SFA
0.75
2,124
06090
MISC FRAMING/SEISMIC HARDWARE -FLOORS
4,325 SFA
0.75
3,244
06100
WALKWAY FRAMING REPAIRISEISMIC HARDWARE- ALLOW
851 SF
2.15
1,830
06100
WALKWAY SHEATHING
851 SF
2.25
1,915
06110
INSTALL JOISTSIBEAMS @ FLOOR '
5 EA
100
500
06160
LVL BEAMS 3-1/2 X 11-1/4
19 LF
17.00
323
06160
LVL BEAMS 5-1/4 X 16
20 LF
36.50
730
06170
2X6 JOISTS @ 24" OC - COMPLETE
86 LF
3.55
305
06170
NEW WOOD POST/COLUMNS
1 EA
200
200
06200
WALKWAY FASCIA
45 LF
15.75
709
07180
WALKWAY WATERPROOFING
851 SF
8.50
7,234
07620
FLASHING WALKWAY
170 LF
9.50
1,615
07620
REPLACE WALKWAY GUTTERS W/NEW
170 LF
20.00
3,400
B10
SUPERSTRUCTURE
DIVISION
TOTAL
24,973 5.77
B20 EXTERIOR CLOSURE
02000
REMOVE, STORE AND RE -INSTALL DOORS
42 SF
25.00
1,050
02000
REMOVE, STORE AND RE -INSTALL WINDOWS
149 SF
20.00
2,980
02000
REPLACE TWO ROWS SIDING ABOVE WALKWAY W/NEW
188 SF
9.00
1,692
05000
HOLDDOWNS-EPDXY
10 EA
135
1,350
06000
NEW RAILING CAP @ DECK
104 LF
15.00
1,560
06110
EXT.WALL-2X6/PLY/INSUWB/GWB - NEW STORAGE
265 SF
15.00
3,975
06160
NEW SHEAR WALLS - FRAMING
225 SF
7.00
1,575
07210
CAULK/SEALANT EXTERIOR DOORS
34 LF
2.95
100
07210
CAULK/SEALANT EXTERIOR WINDOWS
112 LF
2.95
330
07460
CEDARSIDING/TRIM
1,115 SF
9.00
10,035
07900
FLASH/CAULK/TRIM EXT WALL
3,455 SF
2.50
8,638
08100
NEW EXT. WOOD DOOR/FRM/HDWRE-SGL
1 EA
1,250
1,250
08550
WOOD WINDOWS/CLAD - NEW
12 SF
60.00
720
09110
EXT. WALL/SHEAT/INSUWB /GWB-SOUTH ELEV & STORAGE
954 SF
5.75
5,486
09110
MISC BLOCKING/HARDWARE/PREP @ SOUTH ELEV &
954 SF
1.25
STORAGE
1,193
09900
PAINT EXTRIOR DOORSITRIM
11 LVS
90.00
990
12110/2007 U9 AM MEDINA CITY HALL RENOVATION - BASE DETAIL PAGE 1
QUANTITY UNIT UNIT COST
ITEM DESCRIPTION ITEM O B - 1
09900
PAINT EXTRIOR WINDOWS !TRIM
25 EA
100
2,500
09910'
PAINT EXTTERIOR WALLS
3,455 SF
1.85
6,392
09910
SCRAPE AND PREP EXTERIOR WALL -EXISTING
3,076 SF
1.15
3,537
B20
EXTERIOR CLOSURE
DIVISION TOTAL
55,352 12.80
B30
ROOFING
01000
ROOF FASCIA -lX4
40 LF
7,00
280
01000
ROOF FASCIA -lX6
36 LF
10.25
369
01000
ROOF FASCIA -2X12
40 LF
20.00
800
01000
ROOF FLASH/GUTTER/DOWNSPOUT
4,325 SFA
1.75
7,569
06160
PLYWOOD SHEATHING-1/7
229 SF
2.25
515
07100
30# ROOFING FELT @ EXISTING ROOF AND STORAGE
2,989 SF
0.40
1,196
07220
RIGID ROOF INSULATION R-30 @ ROOF
167 SF
3.75
589
07310
CEDAR SHAKE ROOF - NEW
2,989 -SF
8.25
24,659
B30
ROOFING
DIVISION TOTAL
35,977 8.32
C10 INTERIOR CONSTRUCTION
09900
PAINT INTERIORDOORS/TRIM
20 LVS 90.00
1,600
10260
STEEL HANDRAIL @ NE CONC WALL
74 LF 95.00
7,030
10550
FIRE EXTINGUISHER -WI CBNT - ALLOW
1 LS 750
750
10810
TOILET ACCESSORIES - ALLOW
1 LS 500
500
C10
INTERIOR CONSTRUCTION
DIVISION TOTAL
10,080 2.33
C20 STAIRS
05510 PRECAST CONC TREAD EXTERIOR STAIR - OPEN 1 FLT 18,500 18,500
05520 GUARDRAILING @ EXTERIOR STAIR 45 LF 160 7,200
C20 STAIRS DIVISION TOTAL 25,700 5.94
C30 INTERIOR FINISHES
06200
FINISH CARPENTRY/ACCESSORIES
4,325 SFA
0.75
3,244
09000
GWB CEILING @ BATHROOMS
66 SF
7.00
462
09200
GWB @ EXISTING WALL- BATHROOMS
384 SF
3.50
1,344
09250
CEILING PATCH & REPAIR
1,442 SF
0.85
1,226
09310
CERAMIC TILE WALLS
147 SF
12.00
1,764
09380
STONE FLOOR
246 SF
30.50
7,503
09600
FLOOR PREP
3,417 SF
1.25
4,271
09650
MARMOLEUM "LINOLEUM' W/4" HIGH UPTURN
66 SF
7.50
495
09680
CARPET
3,105 SF
4.00
12,420
09700
MISC. PATCH @ EXISTING INTERIOR WALLS
9,382 SF
0.75
7,037
09900
INTERIOR PAINTING - WALLS
9,382 SF
1.75
16,419
09900
PAINT GWB CEILINGS INTERIOR
4,325 SF
1.85
8,001
C30
INTERIOR FINISHES
DIVISION TOTAL
64,185 14.84
D20 PLUMBING
15400 PLUMBING 1 LS 3,557 3,557
D20 PLUMBING DIVISION TOTAL 3,557 0.82
12/10/2007 9:39 AM MEDINA CITY HALL RENOVATION - BASE DETAIL PAGE 2
ITEM DESCRIPTION QUANTITY UNIT UNIT COST T^" A 1 'rn,-
ITEM OB-1
D30 HVAC
15000 HVAC 1 LS 84,339 tt4,JJy
D30 HVAC DIVISION TOTAL 84,339 19.50
D50 ELECTRICAL
16000 ELECTRICAL 1 LS 80,000 80,000
D50 ELECTRICAL DIVISION TOTAL 80,000 18.50
F20 SELECTIVE BUILDING DEMOLITION
02000
DEMO CARPET
3,211 SF
1.00
3,211
02000
DEMO CEDAR SHAKE ROOFIFLASHINGIFELT
2,832 SF
1.95
5,522
02000
DEMO DECK SHEATHING/WATERPROOFING
851 SF
1.15
979
02000
DEMO INT. WALL FINISH @ BATHROOMS
384 SF
1.75
672
02000
DEMO ROOF FASCIA
125 LF
1.75
219
02000
DEMO SIDING/INSULATION/BARRIER
954 SF
1.55
1,479
02000
DEMO STAIRIRAILING - EXTERIOR
i LS
2,500
2,500
02000
DEMO TWO ROWS SIDING ABV WALKWAY
188 SF
1.10
207
02000
DEMO WALKWAY FASCIA
170 LF
1.65
281
02000
MISC DEMO/SAWCUTTING
4,325 SFA
0.55
2,379
02000
REMOVE ROOF GUTTER
193 LF
1.85
357
02000
REMOVE WALKWAY FLASHING
170 LF
1.75
298
02000
REMOVE WALKWAY GUTTER
170 LF
1.75
298
02005
DEMO -METAL HANDRAIL @ NE CONC WALL
13 LF
7.00
91
02125
DEMO TILE FLOORING @ BATHROOM/FOYER
206 SF
2.00
412
02146
REMOVE WOOD POST/COLUMN
1 EA
50.00
50
02220
DEMO-GWB AT CEILINGS
66 SF
1.25
83
06000
DEMO RAILING CAP @ SOUTH AND WEST- WALKWAY
104 LF
2.75
286
F20
SELECTIVE BUILDING DEMOLITION
DIVISION TOTAL
19,321 4.47
G10 SITE PREPARATION
02300 STRIP/GRADEIPREP W/2" LAYER OF GRAVEL -NE OF BLDG 71 SF 2.85 202
G10 SITE PREPARATION DIVISION TOTAL 202 0.05
G20 SITE IMPROVEMENTS
02000
CONCRETE MECH PADS
37 SF
15.00
555
02000
GRAVEL @ S.O.G.-2" DEEP-MECH PAD
37 SF
1.00
37
02315
EXCAVATE AT MECH PADS @ SITE - HAND
8 CY
25.00
200
03000
SITE PATCHING
1 LS
1,000
1,000
03000
TIMBER RETAINING WALL MECH PAD
32 SF
20.00
640
G20
SITE IMPROVEMENTS
DIVISION TOTAL
2,432 0.56
G30 SITE CIVIL / MECHANICAL UTILITIES
02630 AREA DRAIN - COMPLETE 1 EA 875 875
G30 SITE CIVIL I MECHANICAL UTILITIES DIVISION TOTAL 875 0.20
Z10 GENERAL REQUIREMENTS
01000 GENERAL CONDITIONS 3 MO 35,000 105,000
12/10/2007 U9 AM MEDINA CITY HALL RENOVATION - BASE DETAIL PAGE 3
ITEM DESCRIPTION QUANTITY UNIT UNIT COST ". """
ITEM OB-1
Z10 GENERAL REQUIREMENTS DIVISION TOTAL 105,000 24.28
ESTIMATE SUBTOTAL 515,667 119.23
12/10W7 9:39 AM MEDINA CITY HALL RENOVATION - BASE DETAIL PAGE 4
PROJECT: MEDINA CITY HALL RENOVATION - EVIDENCE ROOM
LOCATION: MEDINA, WA
BLDG SF: 53
ESTIMATE: 2007161
EST TYPE: CONSTRUCTION DOCUMENTS
DMSION
DESCRIPTION
TOTAL
$ISF
C10
INTERIOR CONSTRUCTION
774
14.60
C30
INTERIOR FINISHES
193
3.65
D30
HVAC
5,000
94.34
ESTIMATE SUBTOTAL
5,967
112.59
DESIGN CONTINGENCY @
5.00% 298
SUBTOTAL
6,266
ESCALATION TO 23-NOV-07 (8.00%NR) @
1.23% 77
SUBTOTAL
6,343
GENERAL CONTRACTOR'S OH & P @
9.00% 571
_
TOTAL
6,913
130.44
EXCLUSIONS:
SEE ESTIMATE SUMMARY
12/10/2007 9:39 AM MEDINA CITY HALL RENOVATION - EVIDENCE ROOM SUMMARY PAGE 1
PROJECT: MEDINA CITY HALL RENOVATION - EVIDENCE ROOM ITEM 0 B - I
LOCATION: MEDINA, WA
BLDG SF: 53
ESTIMATE: 2007161
EST TYPE: CONSTRUCTION DOCUMENTS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL $ISF
C10
INTERIOR CONSTRUCTION
06120
09900
5/8"GWB WALL -FIRE TAPED
PAINT GWB - WALL
231 SF 1.60
231 SF 1.75
370
404
C10
C30
INTERIOR CONSTRUCTION
INTERIOR FINISHES
DIVISION TOTAL
774 14.60
09250
09900
518" GWB CEILING -FIRE TAPED
°PAINT GWB CEILINGS INTERIOR
53 SF 1.80
53 SF 1.85
95
98
C30
D30
INTERIOR FINISHES
HVAC
DIVISION TOTAL
193 3.65
15000
HVAC - ALLOWANCE PER A/E
1 LS 5,000
5,000
D30
HVAC
DIVISION TOTAL
5,000 94.34
ESTIMATE SUBTOTAL 5,967 11259
12/10/2007 9:39 AM MEDINA CITY HALL RENOVATION - EVIDENCE ROOM DETAIL PAGE 1
ITEM OB-1
CITY OF MEDINA
501 Evergreen Point Road, Medina, WA 98039
(425) 233-6410 www.medina-wa.gov
MEMORANDUM
DATE: March 19, 2007
TO: City Council, City Manager
FROM: Joe Willis Sr., Director of Public Works
RE: Report on City Hall Repair/Expansion
Background
The preliminary report on City Hall and a possible expansion prepared by Johnston
Architects, entitled Medina City Hall Building Survey was provided to the Council in
February of this year. The professional services contract with Johnston Architects
contains two areas of work to be accomplished. The first area of the consultants work
included a condition survey of the existing building, formulation of recommendations for
the correction of deficiencies, and the preparation of drawings and specifications for
the correction work. The second area of the consultants work includes design
development for proposed additions including needs study, conceptual designs and
drawings with specific recommendations, estimated costs, information presentations,
and upon approval, preparation of drawings and specifications for the project and
oversight of the work.
At this point, the architect has completed the building survey, formulated
recommendations and preliminary cost estimates for the repairs which included several
recommended options for the correction work. When reviewing the evaluation team
recommendations in the report, you need to closely examine the existing city hall
condition and the recommendations for its repairs and the correction of deficiencies.
Initial Council comments during the council meeting of February 12th indicated that
while the repairs of the existing building are endorsed by the council, the overall cost
for the renovation and the proposed 25 foot expansion seem excessive and should be
paired down, or at the very least, reviewed for cost saving options. Recognizing that
preliminary cost estimates are only a gage of what the bidding market price may be for
a given scope of work at a specific point in time based upon an experts opinion, the
estimates in this instance should only be utilized as a tool for discussion and
comparison of the options. It is too early in the process to define all of the various
facets of the work involved to accurately estimate the scope of the work or its ultimate
cost when we have not defined all of the work to be accomplished.
When considering the various scopes of work (Study Options) presented in the
consultants report, the first scope of work option should be considered a must. The
second option adds work that a prudent individual would be expected to add to not just
ITEM OB-1
repair the structure but improve the life -safety aspects of the building. The third scope
of work option provides one alternative method of expansion to the building to address
space needs, improve access, work areas, and improve building support functions.
Scope of Work (Study) Options
Scope of Work Option 1 at an estimated cost of $ 435,845 to address the identified
problems and basic life -safety concerns included repairs to the existing building siding,
deck, weather sealing, heating and ventilation, plumbing, electrical and fire alarm
systems, and included minor renovations to the building envelope to upgrade its
structural integrity (primarily at building beam connections, the roof support structure,
and those areas where exterior repair work is needed).
Scope of Work Option 2 at an estimated cost of $ 758503 included all of the Option 1
costs plus additional costs to address seismic and life -safety needs by installing
foundation anchors, added interior shear wall construction to resist seismic collapse, a
fire sprinkler system, and an upgrade of the building lighting and emergency power
circuits.
Both of the above scope of work option cost estimates for the identified repairs and
renovations include architect design fees and contingency funds to arrive at an overall
project cost that includes project development, contingency estimates above and
beyond the estimated construction costs.
Scope of Work Option 3 included Options 1 and 2 costs and the cost to construct a 25
foot extension of both the basement and the main floor levels on the north end of the
building for a total addition of 1875 square feet. The estimated cost of $1,806,199 adds
875 square feet of floor area to each of two levels (not attic level); adds an elevator for
two levels in the existing building for access (not attic level); replaces support columns
in basement to allow optimum use of space, and completes interior renovation work to
maximize the use of the building. It should be noted that continuing to have staff
occupy the attic level with no elevator, emergency exit or fire sprinkler system is not a
desirable situation.
An alternative to provide for the attic emergency exit and to gain usable space in the
existing building is to explore an expansion of the existing attic space using a dormer
or gable system, adding elevator access to the top floor, and adding an emergency
exterior stairway exit. The architect's quick analysis of this option presented in the
attached graphic images does not substantially alter the character of the building while
adding 570 square feet of floor area. The estimated cost for this alternative is
approximately $ 200,000.
Conclusion
I believe that the architect has done an excellent job in identifying immediate building
needs, and while the expansion alternative plan presented in the report requires
refinement, I believe the expansion will not only provide needed space but will also
allow for better space utilization.
ITEM OB-1
The concept of selecting a ceiling budget for the City Hall repairs and renovation and
then backing into a construction option fails to recognize that the existing building
requires repairs and if improvements are accomplished in the same project, they can
be completed at less cost, actually decrease energy usage, improve the building
function, and provide needed space to support City functions. Upon completion, the
City Hall should not make a statement to the community that is pretentious but one that
emphasizes historical importance and regard for the public trust.
It is my recommendation that the Consultant work with the City staff and proceed with
the design development for the building renovation and expansion without
compromising the existing building fagade or character that is to include the necessary
building repairs and life -safety improvements and address the space needs, improve
access, work,areas—and building .support functions. Following staff input and upon
completion of schematic drawings the Consultant is to provide the most cost effective
and efficient floor plan to the Council for consideration.